11:00am- First truck showed up with girder 1-3
11:00am- All bearing pads are set on bents
11:10am- First girder set from bent 1-2
11:30am- Setting the third girder for bent 1
12:40pm- Continue to set I girders 4-6 in between bent 2 and 3
3:47pm- Finished setting girders for the day 7,8,9 in between bent 3 and 4.
4:34pm- Formed and placed rebar for bent 3 and 4 diaphragm
4:40pm- Finished product for the day