Wednesday, March 22, 2017

Site visit-West Corral Rail

 Contractor was ready to pour west corral rail, I inspected the forms and steel placement. First truck arrived at 9:00 am, I tested the concrete: Slump 5", Air 2.8%, we added air then retested 4.8%, Temp 52°. Made three cylinders. Next truck arrived at 9:39 am, I tested the Air 2.5%, we added air 5%. Pour went good. talked with foreman about next visit. He will start placing fill on the south end of the build tomorrow. Headed back at 11:00 am. took cylinders to PPI for testing.



 East Corral rail, looks good. Needs some grout but overall looks good.